1. Project Reports
Bryne Heffner reported on the following:
Parks Master Plan Deliverables include site plan at Fountain, Bucky
Boyle & Roosevelt, next Meeting is on Line January 22nd.
Bogert’s Bridge-Continuing with design, permitting, bid opening Apr
2025, Const 2025-26.
Dixon Bridge, Bid opens in December, construction to start mid
April 2025.
Roosevelt Park Working on moving money to complete demo and
to pavilion.
Jordan Skate Pk, Phase 2, Construction to begin mid April 2025.
MLK Trail working on design, $250,000 grant received, need
significantly more funding, also applied for grant for design of phase
ll to connect to Cedar, will hear in the fall. Additional funding from
Senator Miller for design Phase 2.
Rose Garden- DCED Miller/Schlossberg- Stone repairs at Gazebo
and entrance stairs, upgraded pavilion at Rose Garden #2.
Valenia Pk, Working on history sign.
Working on Swim Lesson Grant.
Complete list of all project status was submitted to Board via email.