Title: R98 Authorization for a change order in the amount of $4,180.00 with Philips & Donovan Architects, LLC to provide preliminary detailed consulting and engineering services for the preliminary design and cost estimates for the City of Allentown regarding the construction of a new Parks Operation facility located in the upper lot of our current Parks Maintenance facility located at 2050 Park Drive, Allentown 18103. The original contract was for $24,480.00, the addition would bring the contract to a new total of $28,660.00.
Sponsors: Administration
Attachments: 1. R98 - Philips & Donovan